Drill-and-blast comprises a cyclical repetition of activities, where each activity involves the use of special equipment. Rock excavation is an industrial process in which the individual phases are optimised and coordinated. Wherever possible, the work is carried out in parallel on more than one front, and the respective cycle on each front is adapted so that staff and machines can switch between workplaces.
Each round of blasting advances the tunnel face.
Blasting Cycle

A drilling jumbo in operation. Photo: Jan Thorén
In good-quality rock, the cross-sectional area of rock caverns can be 600 m2 or more. Sloping tunnels (ramps) are first excavated to reach the different levels in the rock cavern, and then cross tunnels are cut into each level. A pilot tunnel is excavated near the top of the planned cavern, and blasting from this side bench removes the rest of the rock in the upper part.
The underlying benches are then blasted. Bench blasting involves blasting in vertical or horizontal holes, drilled in one or more rows against the rock face.

Illustration: © Tomas Öhrling 2015

© Trafikverket/Project Citybanan. Photographer: Mikael Ullén

Illustration: © Tomas Öhrling 2015
When tunnels and rock caverns are to be built in urban environments, excavation methods with little or no vibration may be needed. Examples of such methods are diamond wire cutting, hydraulic breakers, hydraulic fracturing, expansion chemicals, and water cutting.

The wire cutting technique involves the use of a steel wire with beads impregnated with industrial diamonds, which are strong enough to cut through granite.
© Trafikverket/Project Citybanan. Photographer: Mikael Ullén

Shotcrete can be sprayed dry or wet. In dry spraying, dry cement is delivered by hose to the spray nozzle, where water is added. This provides reinforcement very rapidly, and is suitable for reinforcement measures when the facility is already operational and when the geometry of the tunnel or cavern reduces accessibility.
In wet spraying, ready-mixed cement is pumped through hoses to the nozzle, where compressed air is added. The method provides higher capacity than dry spraying, and thicker layers can be applied. Additives ensure that the quality and hardness of the concrete is comparable with dry spraying. The work environment during wet spraying is more favourable, and there is considerably less material waste. In new production of tunnels and rock caverns, robots are used almost exclusively to spray wet concrete.
By reinforcing shotcrete with fibre, the reinforcement can be created in a single process. In wet spraying, the fibres are added directly in the mixer. The most common type of fibre is made of steel, but plastic fibres are also used.
Fixing anchor bolts into rock is simple and relatively cheap. Rock bolts cast in situ in wet concrete before it sets are rustproof and suitable as permanent reinforcement. The bolt usually comprises a cut corrugated bar, and is often fitted with a plate. A pre-stressed rock bolt is anchored in the bottom of the borehole, and is tightened with a nut and washer at the top end. The bolt can be anchored in the bore hole with wedge anchors or expanders.
Pre-stressed bolts can be fitted quickly and provide immediate support, which is valuable in operational reinforcement. However, as bearing capacity and strength are uncertain over time, these bolts are not suitable for permanent reinforcement.
Friction bolts work as a combination of anchor and pre-stressed bolts. The most common types comprise folded steel tubes or tubes with a slot along their length that are hammered in, creating friction against the inside of the borehole and providing rapid operational reinforcement. Friction bolts are not used for permanent reinforcement.